Aurora West Middle School Project
Project Owner
Aurora Public Schools
Partners
Haselden | General Contractor | Jarrod Fugate | 303-751-1478
Klipp | Architect | 303-893-1990
Alber Engineering | Electrical Engineer | 303-985-3260
Location
Aurora, Colorado
Project Duration
February 2007
Project Scope:
For this nearly $1.7M project, Weifield Group performed an electrical remodel of three existing buildings, and electrical construction for a new addition. The project encompassed 120,000 sq. ft. and included the implementation of site lighting and communication conduits.
Safety
This project encompassed 19,028 man hours, had no recordable accidents, and no lost time.