Steamboat Schools Project
Project Owner
Steamboat Springs School District
Partners
Haselden | General Contractor | Christian Eckstrom | 303-751-1478
Christiansen, Reece, & Partners | Architect | Robert Rody | 719-633-5901
Consulting Engineers | Electrical Engineer | 719-594-0022
Location
Steamboat Springs, Colorado
Project Completion
June 2008
Project Scope:
For this nearly $2.8M project, Weifield Group performed a complete electrical build-out remodel, addition and new construction of three schools and one new elementary school. The project scope included complete lighting control system, security, fire alarm, sound, paging, phone and clock systems.
Safety
This project encompassed 19,251 man hours, had no recordable accidents, and no lost time.