Image Description

Kaiser Permanente

 

Project Owner:

Kaiser Permanente

Partners:

Adolfson & Peterson | General Contractor | 303-363-7101

Locations:

Regional Offices: Denver, CO

Smoky Hill MOB: Aurora, CO

Baseline MOB: Boulder, CO

Longmont MOB: Longmont, CO

Project Duration:

1 month, April 2011

Project Scope:

At each job Weifield demolished the power to the existing chiller, pulled in new wire and terminated to the new chillers. We also changed out the existing motor starters for the pumps with VFD’s.