A shout-out to our team for their fast progress on Weifield’s La Vergne Water System Upgrade project in La Vergne, TN!
This $1.3M project with W&O Construction launched in February 2024 and consists of an upgrade of the city’s SCADA system at the Water Treatment Plant and various remote sites.
The project is currently 20% complete; the team is currently focusing on updating SCADA at the main Water Plant which includes replacing old PLCs, installing new raceways, and completing the wiring. Upgrades are also underway at nine remote sites across the city, including pump stations and pressure stations.
Looking forward to the continued progress — great work, team!