CLIENT: City of Boulder
GC: PCL Construction
ENGINEER: Stantec
PROJECT DURATION: August 2023 – September 2025
PROJECT TYPE: Plan-Spec
DESCRIPTION: Construction of a new hydro cyclone facility and retrofit of the existing dewatering storage tank and aerobic digester. Modifications to the existing aeration basins and solids contact tanks. A new service with MV equipment will be installed to replace two existing aeration blowers, other work to include modification to equipment in the RAS gallery, new fiber routed throughout entire campus and modifications to existing SCADA system.