Cherokee Metropolitan District | Owner

Garney Construction | General Contractor

Burns & McDonnell | Engineer

PROJECT DURATION: January 2021 – December 2022

PROJECT TYPE: Hard Bid

PROJECT DESCRIPTION: This project with is comprised of a new Headworks Building, Chemical Building, Filter Building, and modifications of two existing SBR Basins into continuous flow Bioreactor trains. The Filter Building will also include a Hollow Fiber MBR system and a High Recovery RO system. The integration of a new 480V 2500A switchboard for distribution of these facilities will be included along with medium voltage equipment and cabling to deliver power to an existing 2000kW generator.