City of Longmont | Owner

Glacier Construction Co. | General Contractor

Carollo Engineers | Electrical Engineer

PROJECT DURATION: Feb. 2015 – Nov. 2015

PROJECT TYPE: Water/Waste Water

PROJECT CONTRACT: $767,000

The Longmont Reclamation Facility project involved the replacement of four thickened sludge pumps in the Sludge Control Building and Thickener two Building, as well as the replacement of one primary sludge pump and electrical/instrumentation. This project also included replacement of duplex sump pumps in two locations and replacement of corroded electrical conduits, along with the replacement of a waste gas burner and modification of associated sludge gas process instrumentation.

 