Left Hand Water District | Owner

Moltz Construction | General Contractor

Burns & McDonnell | Engineer

PROJECT DURATION: April 2019 – May 2020

PROJECT TYPE: Water/Waste Water

PROJECT DESCRIPTION: This project is a newly-constructed hydroelectric turbine facility addition to an existing plant. This includes a new electric room fed from the existing plant underground, with a new 480V Panel and a 120V UPS, new lighting and lighting control, and ground grid. Weifield will also be installing a new PLC with fiber optic connections to the existing plant; this will tie in to all the instrumentation and radio equipment.