Tri-State | Owner
Garney Construction | General Contractor
HDR Engineering | Engineer
PROJECT DURATION: Nov. 2017 – March 2018
PROJECT TYPE: Hard Bid
PROJECT DESCRIPTION: This project involved the installation of a fiber duct bank from the water plant to the generation plant installing 3 PLCs.