BVSD COMMUNITY MONTESSORI SCHOOL

Boulder Valley School District | Owner Turner Construction | General Contractor PROJECT DURATION:  Apr. 2017 – Jun. 2017 PROJECT TYPE: Education Interior renovations of the Community [...]

AUTODESK III

AutoDesk | Owner Howell Construction | General Contractor PROJECT DURATION:  Apr. 2016 – Aug. 2017 PROJECT TYPE: Corporate Tenant finish of the 10,809 sq. ft. space located on the 5th floor [...]

ADCO PHASE II

Adams County | Owner FCI Constructors, Inc. | General Contractor PROJECT DURATION: Jan. 2017 – Sept. 2017 PROJECT TYPE: Government Tenant improvement for the Adams County Corrections Facility.

TRI-COUNTY HEALTH

Tri-County Health Department | Owner i2 Construction | General Contractor GreenLight Engineering | Electrical Engineer PROJECT DURATION: Dec. 2016 – Mar. 2017 PROJECT TYPE: Healthcare, [...]

LINCOLN ACADEMY

Jeffco Public Schools | Owner Weifield Group Contracting | General Contractor PROJECT DURATION: Dec. 2016 – Jun. 2017 PROJECT TYPE: Education, Design-Build This project consisted of a full [...]

TUPELO HONEY CAFE

Tupelo Honey Cafe | Owner Story Construction | General Contractor PROJECT DURATION: Nov. 2016 – Mar. 2017 PROJECT TYPE: Retail New construction of café in existing white boxed space in the [...]

ORCHARD CHURCH

Orchard Church | Owner Fransen Pittman | General Contractor The Small Group, LLC | Architect Darr & Collins, LLC | Electrical Engineer PROJECT DURATION:  Dec. 2016 – Aug. 2017 PROJECT [...]

SIERRA ELEMENTARY SCHOOL

Jeffco Public Schools | Owner GH Phipps | General Contractor MOA Architecture | Architect Ackerman Engineering, Inc. | Electrical Engineer PROJECT DURATION:  Sept. 2016 – Jun. 2017 PROJECT [...]

BROOMFIELD WATER LAB

City and County of Broomfield | Owner Saunders Construction, Inc. | General Contractor Short Elliott Hendrickson, Inc. | Electrical Engineer PROJECT DURATION:  Sept. 2016 – Aug. 2017 [...]