CLIENT:  QTS Realty

GC:  Holder Construction

ARCHITECT:  Corgan Associates, Inc.

ENGINEER:  KW Mission Critical Engineering

PROJECT DURATION:  October 2022 – August 2023

PROJECT TYPE:  Design-Assist

DESCRIPTION:  This project includes construction of a multi-phased data center campus. Phase 1 includes a 300,000+ sq. ft. data hall (mostly shell) and associated site infrastructure work, as well as a 3MW Day 1 buildout with an option to build out another 3MW of critical capacity.

Related Projects