GREELEY WEST HIGH SCHOOL: 70% COMPLETE!

Weifield is excited to be working with Adolfson & Peterson Construction (GC) on this design-build, new 257,000 sq. ft. replacement high school project for Weld County School District 6 — on the existing Greeley West High School campus in Greeley, CO!

This project started in September, 2020 and is approximately 70% complete; completion is expected to occur before the new school year starts in August, 2022.

The crew is getting ready to start commissioning the south side of the building and will turn over that half, in March; they are also pulling wire in the auditorium, trimming light fixtures, and completing rough-in on the north side of the building. The one line is 95% complete and there is just one electrical room yet to complete in Area A.

So proud of your progress, Greeley West Team!!

 

 