On Thursday, October 19th, our Industrial team was excited to see the transformer being flown in by crane at our Boulder 63rd Water Treatment Facility project!

This $10.9M project with Archer Western (GC) consists of renovations of the electrical distribution system throughout the campus, high service pump station, raw water strainer vault, replacement of HVAC systems, raw water pump station, etc.

The project is approximately 40% complete; great job to our team for pushing hard to the finish!