EMC

EMC | Owner RJM Construction | General Contractor Priest Engineering | Engineer PROJECT DURATION: April 2012 – September 2012 PROJECT TYPE: Mission Critical, Design-Assist PROJECT [...]

CENTURY LINK

Century Link | Owner Howell | General Contractor BCER Engineering | Engineer PROJECT DURATION: September 2012 – October 2012 PROJECT TYPE: Mission Critical PROJECT DESCRIPTION: Data center [...]

RED SQUARE DATA CENTER

Holder Construction Company | Owner Platt Rogers Construction | General Contractor TiePoint Engineering | Engineer PROJECT DURATION: June 2014 – August 2014 PROJECT TYPE: Mission Critical [...]

T-MOBILE

Roebbelen Contracting, Inc. | Owner PROJECT DURATION: December 2014 – January 2015 PROJECT TYPE: Mission Critical PROJECT DESCRIPTION: Installation of a demising wall to separate an [...]

LOCKHEED MARTIN DATA CENTER

Lockheed Martin | Owner Tyco Westfire | General Contractor PROJECT DURATION: October 2015 – November 2015 PROJECT TYPE: Mission Critical PROJECT DESCRIPTION: Upgrades to the fire alarm [...]

H5 DATA CENTER

H5 Data Centers | Owner H5 Data Centers | General Contractor PROJECT DURATION: April 2016 – June 2016 PROJECT TYPE: Mission Critical PROJECT DESCRIPTION: Lighting retrofit for H5 Data [...]

ESC DATA CENTER

Adams 12 School District | Owner Rand Construction | General Contractor RMH Group | Engineer PROJECT DURATION: December, 2014 PROJECT TYPE: Mission Critical PROJECT DESCRIPTION: Replacement of [...]

E.ON (TX)

E.ON/Bob Campbell | Owner Harvey Cleary | General Contractor Bay and Associates/Joanne Hoban | Engineer PROJECT DURATION: April 2019 – December 2019 PROJECT TYPE: Corporate PROJECT [...]