Holder Construction Company | Owner
Platt Rogers Construction | General Contractor
TiePoint Engineering | Engineer
PROJECT DURATION: June 2014 – August 2014
PROJECT TYPE: Mission Critical
PROJECT DESCRIPTION: Upgrades to a general fueling center. Provided and installed 2 ea. 60,000 gallon fuel tanks, as well as 6 capable diesel generators (3 installed) each of which provide 1,600+ horsepower and 221 gallons of fuel per hour.