Kaiser | Owner

Alvarado Construction | General Contractor

PROJECT DURATION: April, 2020 – May, 2020

PROJECT TYPE: Healthcare, Design-Build

PROJECT DESCRIPTION: Boring from building envelope to disconnect location. Core drilling of exterior wall for conduit entrance into building. Installation of conduit runs inside the building. Conduit and conductors to nearest electrical panel with available load to feed the remote disconnect. Empty conduit to MDF/IDF room for use by others. Installation of line voltage conductors in bored conduit to remote disconnect location. Terminations at both panel and remote disconnect. M.O.P. and scheduling of shutdowns and cut overs.