FifteenFortySeven | Owner

Sampson Construction | General Contractor

BALA Consulting Engineers | Engineer

PROJECT DURATION: November 2018 – January 2019

PROJECT TYPE: Mission Critical

PROJECT DESCRIPTION: This project is a Phase 3 tenant improvement and expansion of the Green House Data facility including the installation of a 900kw UPS, an 8,000 sq. ft. data center, and upgrades to main switchgear, distribution gear, lighting, and cable tray systems.